Bid Letting Information
WYDOT Contractor's Desktop Download Instructions Date Modified: March 19, 2013
Contractor's Desktop Tutorial Tutorial Instructions Download Viewer
DBE File for Contractor's Desktop Download Instructions Date Modified: August 22, 2014
To obtain a complete printed Planholder's list, set the print orientation to Landscape.
To View/Download Plans, click on the link to the right.



Scheduled letting for December 10, 2014
Call Order 1 Version Number: 1
Project Number: NHPPI-I902120
Description: Buffalo - Gillette (Power River East)
County: Johnson
Engineer: Isaac Finkle, P.E.
Engineer's Phone Number: (307)684-2505
Completion Date: June 30, 2017
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 2 Version Number: 1
Project Number: NHPPI-I253113
Description: Douglas - Glenrock (Douglas West, NBL)
County: Converse
Engineer: James Barnes, P.E.
Engineer's Phone Number: (307)358-5515
Completion Date: October 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 3 Version Number: 1
Project Number: SCP-TC-0103039
Description: Snowy Range (County Line Section)
County: Albany; Carbon
Engineer: Kory Cramer, P.E.
Engineer's Phone Number: (307)745-2137
Completion Date: August 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 4 Version Number: 1
Project Number: SCP-TC-P221050
Description: Walcott Junction - Saratoga (WYO 130)
County: Carbon
Engineer: Jake Lonn, P.E.
Engineer's Phone Number: (307)328-4103
Completion Date: October 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 5 Version Number: 1
Project Number: STP-1602017
Description: Chugwater - Hawk Springs (Chugwater East)
County: Goshen; Platte
Engineer: Buck Klemola, P.E.
Engineer's Phone Number: (307)532-1251
Completion Date: October 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 6 Version Number: 1
Project Number: NHPPI-I901119
Description: Sheridan - Buffalo (Meade Creek & Marshall Hill Slides)
County: Sheridan
Engineer: Jerry Buckley, P.E.
Engineer's Phone Number: (307)674-2326
Completion Date: May 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums: # 1
Scheduled letting for December 10, 2014
Call Order 7 Version Number: 1
Project Number: SCP-TRFSIGN
Description: I-80 Logo Signs (Districts 1 & 3)
County: Albany; Carbon; Laramie; Sweetwater; Uinta
Engineer: Steven Cook, P.E.
Engineer's Phone Number: (307)745-2115
Completion Date: October 31, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 8 Version Number: 1
Project Number: DR42133
Description: Sundance - So. Dakota State Line (County Road Overpass)
County: Crook
Engineer: Warren Oyler, P.E.
Engineer's Phone Number: (307)283-1135
Completion Date: February 28, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:
Scheduled letting for December 10, 2014
Call Order 9 Version Number: 1
Project Number: STP-BR-2000054
Description: Wilson - Idaho (Fish Creek Structure)
County: Teton
Engineer: Bob Hammond, P.E.
Engineer's Phone Number: (307)733-3665
Completion Date: April 30, 2015
View Notice to Contractors
View Bid Items
View Planholder's List
Download Proposal
View Addendums:

Copyright © 2009 State of Wyoming. All rights reserved.

| Copyright | Privacy Policy | Contact WYDOT